Turnover Process
The turnover process is the most important to a new homeowner, because this is when
the property finally changes hands. Because we know how important this is to you, we'd like to share some guidelines to make the transition smooth and satisfactory for both parties.
Turnover Process
1.Completion of unit will commence upon issuance of Authority-To-Turnover (CLEARANCE) by Documentation
2.Completion date:
1.Thirty (30) days for single condominium unit
2.Forty-five (45) days for tandem condominium units
3.Approximately Nine (9) months for unit construction
3.Punchlisting/inspection by the client will be scheduled after the completion date
4.Rectification of punchlisted items will be done immediately but completion date may vary depending on the nature of the punchlisted items
5.Client is responsible in settling all required fees & deposits prior to unit turnover
6.Homeowner Orientation of community house rules, policies & regulations is done during handover of unit
7.Handover kit and welcome gift is given to client upon acceptance of unit
8.Upgrade/improvements for his unit will be allowed only after the acceptance of unit
9.Note that certain warranties may be voided by any unit material alteration
Requirements prior to issuance of CLEARANCE
1.Payment of the minimum downpayment required
2.Issuance of required post dated checks for the balance of Total Contract Price
3.Submission of duly signed CONTRACT TO SELL / DEED OF ABSOLUTE SALE & other pertinent documents
4.Letter of Guarantee (LOG) & Drawdown/Loan Take-out (for external bank financing only)
Required Fees & Deposits
1.MERALCO Service Deposit for permanent power connection
2.Real Property Tax (RPT) – client’s share
3.Cash Bond for temporary power (if permanent power service is not yet available)
4.Condominium Corporation fees & dues
Requirements for a PERMANENT POWER CONNECTION
1.Proof of ownership (CTS/DOAS or CCT)
2.Duly accomplished MERALCO application form
3.Two (2) valid IDs
4.Duly signed MERALCO waiver
5.Authorization letter (if accomplished thru representative)
Condominium Corporation
FEES & DUES
1.One time Joining/Membership fee
2.Monthly Association dues
3.Construction bond (for unit with owner’s upgrade)
4.Insurance premium
5.RPT of common areas
6.Other Condominium Corporation assessments
Turnover Process
The turnover process is the most important to a new homeowner, because this is when
the property finally changes hands. Because we know how important this is to you, we'd like to share some guidelines to make the transition smooth and satisfactory for both parties.
Turnover Process
1.Completion of unit will commence upon issuance of Authority-To-Turnover (CLEARANCE) by Documentation
2.Completion date:
1.Thirty (30) days for single condominium unit
2.Forty-five (45) days for tandem condominium units
3.Approximately Nine (9) months for unit construction
3.Punchlisting/inspection by the client will be scheduled after the completion date
4.Rectification of punchlisted items will be done immediately but completion date may vary depending on the nature of the punchlisted items
5.Client is responsible in settling all required fees & deposits prior to unit turnover
6.Homeowner Orientation of community house rules, policies & regulations is done during handover of unit
7.Handover kit and welcome gift is given to client upon acceptance of unit
8.Upgrade/improvements for his unit will be allowed only after the acceptance of unit
9.Note that certain warranties may be voided by any unit material alteration
Requirements prior to issuance of CLEARANCE
1.Payment of the minimum downpayment required
2.Issuance of required post dated checks for the balance of Total Contract Price
3.Submission of duly signed CONTRACT TO SELL / DEED OF ABSOLUTE SALE & other pertinent documents
4.Letter of Guarantee (LOG) & Drawdown/Loan Take-out (for external bank financing only)
Required Fees & Deposits
1.MERALCO Service Deposit for permanent power connection
2.Real Property Tax (RPT) – client’s share
3.Cash Bond for temporary power (if permanent power service is not yet available)
4.Condominium Corporation fees & dues
Requirements for a PERMANENT POWER CONNECTION
1.Proof of ownership (CTS/DOAS or CCT)
2.Duly accomplished MERALCO application form
3.Two (2) valid IDs
4.Duly signed MERALCO waiver
5.Authorization letter (if accomplished thru representative)
Condominium Corporation
FEES & DUES
1.One time Joining/Membership fee
2.Monthly Association dues
3.Construction bond (for unit with owner’s upgrade)
4.Insurance premium
5.RPT of common areas
6.Other Condominium Corporation assessments
turnover_fees.pdf | |
File Size: | 43 kb |
File Type: |
Buyer Acceptance
If the buyer fails to inspect and accept the unit within thirty (30) days from the date of notice that the unit is ready for turnover, it shall be deemed that the buyer has automatically accepted the unit.
Acceptance by a Representative
If the registered buyer is not available on the scheduled turnover of unit, his/her duly authorized representative can accept the unit in his/her behalf. The representative must be designated as a duly notarized Special Power of Attorney (SPA).
The unit turnover cannot be delayed on account of SPA’s availablity schedule
Turnover Schedules
A unit is deemed completed upon the issuance of the Authority to Turnover Documentation. (CLEARANCE)
Completion Date:
1.Thirty (30) days for a single condominium unit
2.Forty-five (45) days for a tandem condominium unit
3.Approximately nine (9) months for unit construction.
Once the unit has been declared complete, you may then proceed to inspect and punchlist your new home to check if everything agreed upon is in place.
Things to know about the Turnover Process
1.In case some things in the unit need to be rectified following your inspection, these will be done immediately. However, the completion date may vary, depending on the nature of the things to be fixed.
2.To avoid any delays with the turnover process, please make sure that all required fees and deposits are taken care of before unit turnover.
3.Homeowner Orientation of the community house rules, policies and regulations will be done during the unit turnover. Likewise, the handover kit and welcome present is given upon your acceptance of the unit.
4.Upgrades, improvements and other personal modifications to your unit may only be allowed after the official acceptance. Please bear in mind that certain warranties may be voided by alterations.
If the buyer fails to inspect and accept the unit within thirty (30) days from the date of notice that the unit is ready for turnover, it shall be deemed that the buyer has automatically accepted the unit.
Acceptance by a Representative
If the registered buyer is not available on the scheduled turnover of unit, his/her duly authorized representative can accept the unit in his/her behalf. The representative must be designated as a duly notarized Special Power of Attorney (SPA).
The unit turnover cannot be delayed on account of SPA’s availablity schedule
Turnover Schedules
A unit is deemed completed upon the issuance of the Authority to Turnover Documentation. (CLEARANCE)
Completion Date:
1.Thirty (30) days for a single condominium unit
2.Forty-five (45) days for a tandem condominium unit
3.Approximately nine (9) months for unit construction.
Once the unit has been declared complete, you may then proceed to inspect and punchlist your new home to check if everything agreed upon is in place.
Things to know about the Turnover Process
1.In case some things in the unit need to be rectified following your inspection, these will be done immediately. However, the completion date may vary, depending on the nature of the things to be fixed.
2.To avoid any delays with the turnover process, please make sure that all required fees and deposits are taken care of before unit turnover.
3.Homeowner Orientation of the community house rules, policies and regulations will be done during the unit turnover. Likewise, the handover kit and welcome present is given upon your acceptance of the unit.
4.Upgrades, improvements and other personal modifications to your unit may only be allowed after the official acceptance. Please bear in mind that certain warranties may be voided by alterations.